Timeline
Note that this timeline is subject to change and will be updated as appropriate.
April 2019
Utah Legislature passes HB 411, enabling the Community Renewable Program (CRP).
December 2019
Utah Public Service Commission adopts administrative rules to enable CRP.
2021
February 2021
Action: Distribute Governance Agreement (GA) for signature to committed communities.
July 2021
Decision: Does eligible local government sign GA and pay Phase 1 cost? Allows voting on utility program design.
2022
January 2022
Last Chance Decision:
Does eligible local government sign GA and pay Phase 1 cost? No more changes to utility program design.
Decision: Does participating local government sign the Utility Agreement (UA)?
Action: Submit joint program application to Utah Public Service Commission (PSC).
July 2022
Action: Participating local governments pay Phase 2 cost.
September 2022
Decision: Does Utah PSC approve program application?
December 2022
Decision: Does participating local government pass required ordinance within 90 days?
Action: Issue Request for Proposals (RFP) for new renewable energy resource.
March 2023
Decision: Execute RFP for new renewable energy resources?